New York City Transit (NYCT) Clark Street Tube Repair and Resiliency Project

New York, N.Y.

Project Value:
$72M

PP#: 0000 – 0000 

Start & End Dates:
2016 – 2018

Reference:
Mr. Philip McGrade, PE
Senior Project Manager
The LiRo Group
111 Broadway
New York, N.Y. 10006

C: 718.873.5526

E: mcgradep@liro.com

PACO serves as the linchpin that keeps construction projects on track and ensures successful outcomes. Here we showcase projects that are either ongoing, or that have been executed efficiently while maintaining the highest standards of quality.

The Clark Street Tube Rehabilitation Project restored and upgraded two 1.2-mile-long subway tunnels damaged by Superstorm Sandy’s saltwater flooding. As part of the MTA’s resiliency program, the project replaced critical communications, signal, and power infrastructure, rehabilitated pump rooms, installed a new emergency pumping system, and waterproofed and relocated vulnerable equipment to reduce future flood risks. Weekend service reroutes on the 2 and 3 lines enabled crews to complete these essential repairs while maintaining weekday operations and improving the tunnel’s long-term reliability and resilience.

The PACO Group team gathers around a conference table to discuss strategies.

PACO SERVICES

01. Cost Estimating 

02. Scheduling Services

03. Inspection Services