New York City Transit (NYCT) Clark Street Tube Repair and Resiliency Project
New York, N.Y.
Project Value:
$72M
PP#: 0000 – 0000
Start & End Dates:
2016 – 2018
Reference:
Mr. Philip McGrade, PE
Senior Project Manager
The LiRo Group
111 Broadway
New York, N.Y. 10006
The Clark Street Tube Rehabilitation Project restored and upgraded two 1.2-mile-long subway tunnels damaged by Superstorm Sandy’s saltwater flooding. As part of the MTA’s resiliency program, the project replaced critical communications, signal, and power infrastructure, rehabilitated pump rooms, installed a new emergency pumping system, and waterproofed and relocated vulnerable equipment to reduce future flood risks. Weekend service reroutes on the 2 and 3 lines enabled crews to complete these essential repairs while maintaining weekday operations and improving the tunnel’s long-term reliability and resilience.
PACO SERVICES
01. Cost Estimating
02. Scheduling Services
03. Inspection Services