New York City Transit, 148th Street Yard Resiliency Project

New York, NYv

Project Value:
$15M

Start & End Dates:
2014 – 2019

PP#: 0000-0000 

Reference:
Vincent Cassano
Principal
Jacobs
2 Penn Plaza
Suite 0603
New York, NY 10121

Ell: (914) 819-8896
E: vincent.cassano@jacobs.com

PACO serves as the linchpin that keeps construction projects on track and ensures successful outcomes. Here we showcase projects that are either ongoing, or that have been executed efficiently while maintaining the highest standards of quality.

PACO Group, as a subconsultant to Jacobs, was awarded a contract to perform engineering services for repair and resiliency projects related to Superstorm Sandy.

Due to the relatively low elevations of the 148th St Yard with respect to the Harlem River, the yard seawall next to the riverfront was recently reconstructed to a higher elevation. The actual water level during Superstorm Sandy reached a reported elevation of 6 inches, just below the crest of the unfinished new walls which are designed for category 1 storm protection. Water entered the yard through gaps in the unfinished walls and damaged power cables, hand switches and duct banks.

To meet the requirements for category 2 storm protection, the project entails raising the recently completed flood walls and extending the flood protection walls for the yard. In addition, the project will also include protection of the tunnels from flooding by installing a protection barrier at the tunnel portal

PACO’s services included Inspection, Mechanical Engineering, Procurement Support, Estimating, Risk Assessment, Systems Engineering and Track/Signals Engineering.